When MERMEC set out to install a laser-based Wheel Profile Measurement System in close proximity to the Eurotunnel, they faced a critical challenge: how to avoid unintended laser exposure without compromising the system’s ability to inspect up to 200 trains per day. To meet these requirements, MERMEC partnered with Frauscher.

In 2025, MERMEC commissioned the installation of a high-speed, laser-based Wheel Profile Measurement System for trains entering the Eurotunnel. This system  can scan up to 150 axles per train for nearly 200 trains per day, at speeds up to 62 mph (100 km/h). The constrained track layout leaves no room for protective barriers, creating a critical safety risk of unintended laser exposure to passengers and nearby trains.

To address this challenge, MERMEC partnered with Frauscher to utilize the Frauscher Advanced Counter FAdC and Wheel Sensors RSR123. Frauscher developed a fully integrated, fail-safe solution that directly interfaces with MERMEC’s laser system. The system dynamically activates and deactivates laser emissions in real time based on train presence, monitored through two critical track sections. Relay outputs are configured to default to a safe state in the event of power loss or faults, ensuring maximum protection.

Delivered as a pre-configured, tested cubical, the solution simplified deployment and minimized the on-site installation effort. Frauscher provided full support during commissioning and handover, enabling seamless integration. By combining precise axle counting with automated laser control, the project delivered a safety certified and future ready setup that eliminates manual intervention and mitigates the risk of accidental laser exposure. This ensures reliable, high-speed wheel inspections in a busy mainline environment.

Partnering with Frauscher on the prestigious Eurotunnel project highlights the power of combining complementary strengths. By bringing our advanced expertise and innovation capabilities together with Frauscher’s renowned know-how, we created a synergy that enabled us to tackle complex challenges and deliver exceptional results.
Enrico Betterle

MERMEC

Dual-track monitoring

The FAdC monitors both adjacent track sections in parallel, enabling precise control of laser triggering based on real-time train detection.

Fail-safe safety logic

Relay outputs are designed to default to a safe state during outages, preventing unintended laser operation.

Turnkey system integration

Solution was delivered in a pre-configured and fully tested cubical, ready for deployment, with installation support included.

Dynamic control for live environments

The intelligent interface ensures that laser systems only activate when safe to do so, which is crucial in busy mainline applications.

Future-ready platform

The flexible internal logic of the FAdC allows the system to be customized according to the operator´s needs, offering a flexible and reliable solution.

Similar Projects
This might also interest you
1/5
Train DetectionUnited States of America

Class 1 Yard Project

Frauscher was approached by a North American Class 1 railroad planning a major expansion of one of its yards, and the required time to completion was short. The scope of the expansion was to build an operational multitrack flat yard on vacant land within six weeks with a signalling solution to protect switches during operations.
Train DetectionCanada

Toronto Transit Commission

The Toronto Transit Commission (TTC) Line 1 Yonge-University is Toronto’s longest subway line, with track circuits utilized for signalling. Due to an increasing number of daily passengers and an aged system the need for upgrading without interfering with the daily operations became readily apparent. It was further required that the new signalling system functions independently of the existing system. It would provide CBTC fallback functionalities, and work as an overlay to the current track circuit-based system.
Train DetectionIndia

Ensuring reliable rail operations across India´s longest railroad bridge

The Bogibeel Bridge is India’s longest railroad bridge that connects Assam and Arunachal Pradesh, carrying both rail and road traffic across the Brahmaputra River. Harsh environmental conditions and structural constraints made conventional signaling impractical. The Frauscher Advanced Counter FAdC axle counting system was selected for its proven reliability and low maintenance requirements, even in challenging conditions.
Train DetectionCanada

Edmonton Metro Line

The Edmonton Metro Line was experiencing significant issues with its newly installed Communications Based Train Control (CBTC) signalling system, which did not perform to the operator‘s expectations. The city was forced to run an incomplete schedule with reduced train speed and frequency which negatively affected commuters and the city of Edmonton in general. Finally in 2019, the operator decided to install a new system in cooperation with Frauscher.
Train DetectionUnited States of America

Frauscher Track Vacancy System FTVS Testing

During the initial development phase of the Frauscher Track Vacancy System FTVS, a number of pre-production units were released for real-world testing to examine their performance in typical yard environments. Consequently, several trials were conducted in the United States.